Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 16, 2024 - 03:01 UTC
Scheduled
To fully restore the redundancy in our network infrastructure at the São Paulo Data Center, we will conduct maintenance on a switch in the Distribution Layer.
Maintenance Schedule: Start Date: Aug 16th Start Time: 03:01 AM UTC End Time: 09:01 AM UTC Duration: 6 hours
During this maintenance window, you may experience: - Service disruptions: Brief spikes, drops, and interruptions due to traffic switchover. - Maximum outage: Up to one hour of cumulative downtime.
While the risk of network downtime is minimal, it could happen. We understand that disruptions can be inconvenient. We are committed to minimizing the impact and mitigating the risk of outages.
Posted Aug 14, 2024 - 20:05 UTC
This scheduled maintenance affected: Regions (SAO (Sao Paulo)).