Ashburn Electrical Maintenance Notice

Scheduled Maintenance Report for Latitude sh

Completed

The scheduled maintenance has been completed.
Posted Sep 18, 2026 - 11:00 UTC

Update

Scheduled maintenance is still in progress. We will provide updates as necessary.
Posted Sep 14, 2026 - 19:51 UTC

Update

Scheduled maintenance is still in progress. We will provide updates as necessary.
Posted Sep 14, 2026 - 19:47 UTC

Update

Scheduled maintenance is still in progress. We will provide updates as necessary.
Posted Sep 14, 2026 - 19:44 UTC

Update

Scheduled maintenance is still in progress. We will provide updates as necessary.
Posted Sep 14, 2026 - 19:43 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 14, 2026 - 14:30 UTC

Scheduled

On September 14 - 18, 2026, starting at 07:00 EDT each day, our Ashburn datacenter provider will upgrade the building's critical power system. The work is performed on one power lineup at a time (about one day each), and affected cabinets will temporarily run on a single power feed.

No downtime is expected and no customer action is required, though power redundancy will be reduced during the work.

Updates will be posted here.
Posted Sep 14, 2026 - 14:29 UTC
This scheduled maintenance affected: Regions (ASH).